Calculation For LOCO (Power) Requirement Under Power Plan

 



1. To be prepared once in six months.

 

2. Avg. No. of trains run on each section per day and Avg. hours on road for last six months duly signed by Senior DME(P) and Senior DOM to be prepared.

3. Formula: Section wise average freight POL for the last six months to be calculated as under:

Bare POL = PDD + HOR + PAD

 

Where POL= Power on line.

PDD = Pre departure detention.

HOR = Hours on road; PAD = Post arrival detention

 

4. 3.5 % further growth and 10% Bunching allowance to be demanded on Bare POL

 

5. Loco's requirement. for DMT. ART. and other loco' s which remain in outage but not added in POL for the purpose of calculation of average kilo meters to be added in the bare requirement.

 

6. To arrive total POL. last six-month average POL of shunting loco link WDS-4, WDS-5 pilots and Mail lie over to be added in the POL calculated above.

 

7. Mail/ Exp./ Pass. Loco requirement to be worked out based on loco link. Add 10% for major repair allowance.

 

8. For shunting services, work out number of points for 8 hours shunting, demand 0.33 POL. Add 1 loco as overlap against 06 loco. Add 10% for major repairs.


9. Kms formula: Total kms earned on the Avg. per day during last six months divided by average loco utilization.



RAIL NEWS CENTER

RAIL EMPLOYEE INFORMATION


Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.

.