WORKING OF TRAIN IN GHAT SECTION (GR-3.50/SR-3.50-1)
Working of train in Ghat section is mentioned in the working time table (WTT) of the Division. The detailed instructions on train operation will be incorporated in the SWR of the station situated in the Ghat section. Pre-caution to be taken while working of train in Ghat section:-
1. The marshalling of train running in the Ghat section must be as per the rules.
2. On goods train the loaded wagon should be attached next to engine and empty wagon behind it.
3. No four wheeler shall be attached in between two eight wheeler on in between engine and wagon.
4. Train running on Ghat section should not exceed the authorized load.
5. The train should not be run without banker engine in Ghat section where such engine is to be attached as per the special instruction.