TRAIN PARTING

TRAIN PARTING (GR 6.08 and SR – 6.08-1) 


Train parting

1. Meaning-

 Any portion of the train, if becomes detached while in motion is called train parting.

2. Loco Pilot

I. If the Loco Pilot comes to know that the train has parted, he should put on the flasher light and give long – short - long – short (---0—0) whistle repeatedly to attract the attention of the Guard till acknowledged by the Guard. He should keep the front portion of the train moving until the rear portion of the train has come to a stand. The guard shall acknowledge the loco pilot by waving up the and down a green signal by day and white light by night and shall promptly apply hand brake of the brake van. 

II. If both the portion has come to a stand on a single line section, the loco pilot will depute the Asst- Loco Pilot to protect the train in front and the Guard shall protect the train in rear. 

3. Guard

 If the Guard comes to know that the train has parted, he shall promptly apply hand brake of the brake van and then signal to the Loco Pilot by waving up and down a green signal by day and white light by night. The Loco Pilot must acknowledge this signal with ---0—0 whistles and use his judgment to keep the front portion of the train in motion until the rear portion has come to a stand. As soon as the rear portion has come to a stand in the section, the Guard must protect it both in rear and in front. If the front portion is out of sight, in accordance with G.R 6.03. 

4. Loco Pilot of Banking Engine-

 If there is a banking engine in the rear, the loco pilot of the banking engine when discover the parting, must bring the rear portion to a stand and at the same time repeatedly sounds – 0—0 whistle to attract the attention of the loco pilot of the leading engine. The loco pilot of the banking engine will protect the rear portion and the guard will protect the train in front. 

5. Gate Man-

 If a gateman observe a train running in two or more portions, he will draw the attention if the loco pilot and the Guard by shouting and / or whistling. He should also show green hand signal during day and white light by night waving up and down vertically as high and as low as possible. He should show no other signals. Should he fails to attract the attention of the Loco Pilot and if there is sufficient distance between the parted portion of the train, he must place three detonators on the line at a distance 10 meters apart for the following portion or the portions to attract the attention of the Guard by shouting and/ or whistling. 

6. Station Master

a) If the Station Master notice a train is running in two or more portions, he will endeavor to attract the attention of the Loco Pilot and Guard by waving green up and down a green signal by day and white light by night. If there is sufficient time between the two portions, he shall place three detonators at 10—10 meters apart between two parts to attract the attention of the Guard.

b) If the two portion enter the block section, the SM shall give the train divided signal (6-3 beats) to the station ahead. 

c) The SM of the Station in advance shall acknowledge the signal by giving6-3 beats, He shall receive the train directly into the station on a vacant line and immediately inform the Station in rear5 that the train has parted and that the rear portion may roll back towards the later. If however the rear portion following the front the SM must place 3 detonators on the liner and endeavor to bring it to stand by hand brake, or by heaping up earth on the rails or other suitable means or divert it, if possible to a vacant line. 

d) The Points shall be set to the sand hump or derailing switch. But in case of passenger train, it shall be allowed to proceed ahead. 

e) If there is no vacant line after receiving the first portion then the rear portion shall be tried to stop by heaping up earth on the rail and BWM 4.11 shall be followed. 

6) When both the portions of the parted train are brought to stand and it is possible to couple then up, the Guard will be responsible for bringing the two portions together in a safe and proper manner. 

7) Parted load will not be coupled if the number of wagons in rear portion is 10 or less in four wheeler stock and 5 or less in eight wheeler stocks. In such case, SR. 6.09-1 will be followed to clear the load. In case where there is banking loco in rear, the load can be re-coupled. 

The Train Divided Signal Code (BWM 4.11) 

a) On seeing the train running in two or more portions, 6—3 beats must be sent to the station in advance.

b) On receiving the signal the SM shall acknowledge and place the signals at danger to prevent any train from the opposite direction proceeding towards the station from which such signal is received. The train going in opposite direction must not be allowed to proceed until it has been ascertained that the line on which it is not obstructed. 

c) He shall take prompt steps to bring the first portion to a halt ant take all measures to bring the second portion to a stop. He shall place three detonators at 10 meters on the line to attract the attention of the Guard in second portion. 

d) The SM who has received 6—3 beats shall take immediate steps to receive the first part on the station and the second part on a vacant line or on a siding. 

e) If stoppage of the first portion would risk a collision, it may be allowed to proceed ahead by waving a green signal by day and a white signal by night slowly, provided the line ahead is clear and there is no falling gradient ahead. 

f) If the block section ahead is obstructed, then every possible step shall be taken to stop the first part on the station. 

g) If a train is parted while starting and the LP runs forward with the first portion, the “stop and examine the train” 6—1 beat signal must be sent to the station in advance and not “train divided” 6—3 beats signal. h) The block section must not be cleared until vehicles of the parted train have arrived at either end of the block section and the line is safe for traffic.
Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.

.


Labels

TRAFFIC (41) Control Organisation (6) Duty of Operating Staff (6) INDEX (6) Specification (5) Abnormal Working (3) CAUTION ORDER / SPEED RESTRICTIONS (3) Question Bank (3) Railway (3) TNC (3) 01.035 Duty of Points Man/Shunt Man (2) 04.03. OPERATING STATISTICS (2) Accident (2) Automatic Signal (2) Break Binding (2) Crank Handle (2) FREIGHT OPERATIONS INFORMATION SYSTEM (FOIS) (2) Operating (2) Question with Answer (2) Safety Device (2) tnc. (2) 001. प्रस्तावना (1) 0010. स्टेशन संचालन नियम की अभिस्वीकृति रजिस्टर (क्र. 1 ) (1) 0011. कर्मचारी वैयक्तिक विवरण रजिस्टर (क्र. 2 ) (1) 0012. कर्मचारी परामर्श रजिस्टर (क्र. 3 ) (1) 0013. निरिक्षण रजिस्टर (क्र. 5 ) (1) 0014. एस एंड टी खराबी रजिस्टर (क्र. 7 ) (1) 0015. सतर्कता आदेश रजिस्टर (क्र. 8) (1) 0016. एस एंड टी खराबी मेमो बुक (क्र. 9 ) (1) 0017. दुर्घटना रजिस्टर (क्र. 11 ) (1) 0018. सतर्कता आदेश मैसेज बुक (क्र. 13) (1) 0019. संरक्षा तथा रजिस्टर (क्र. 14) (1) 002. स्टेशन मास्टर / उप स्टेशन मास्टर की ड्यूटी लिस्ट (1) 0020. डिस्कनेक्शन तथा रिकनेक्शन रजिस्टर (क्र. 15) (1) 0021. आपातकालीन क्रास ऑवर टेस्टिंग रजिस्टर (क्र. 16 ) (1) 0022. रिले रूम चाबी रजिस्टर (क्र. 19 ) (1) 0023. संयुक्त पाइंट एंड क्रासिंग रजिस्टर (क्र. 20) (1) 0024. संयुक्त ट्रैक सर्किट रजिस्टर (क्र. 20 A) (1) 0025. असामान्य संचालन रजिस्टर (क्र. 21 ) (1) 0026. स्टेबल लोड रजिस्टर (क्र. 22 ) (1) 0027. सिक बैगन रजिस्टर (क्र. 26) (1) 0028. क्रेक हैंडल टेस्टिंग रजिस्टर (1) 0029. इंजीनियरिंग एवं पॉवर ब्लाक रजिस्टर (1) 003. व्यक्तिगत परिचय (1) 0030. विभिन्न प्रकार के काउंटर नम्बर रजिस्टर (1) 0031. पैनल ब्लाक होने पर - स्टेशन मास्टर के कर्तव्य (1) 0033. गाड़ी संचालन से संबंधित महत्वपूर्ण अधिकार पत्र (1) 0034. स्टेशन परिचालन रजिस्टर के संरक्षण की सामान्य अवधि (1) 0035. घंटी कोड (1) 0037. दोहरी लाइन पर इकहरी लाइन का संचालन (1) 0038. कार्यभार सौपते समय तथा कार्यभार लेते समय ली जाने वाली सावधानियां (1) 0039. संरक्षा उपस्कर (1) 004. पूनश्र्चर्या पाठ्यक्रम (1) 0041. शंटिंग के दौरान ली जाने वाली सावधानियां (1) 0042. विभिन्न प्रकार के ब्लाक में लि जाने वाली सावधानियां (1) 0045. अग्रदाय राशि (1) 0046. सिग्नल पार करने (SPAD) पर स्टेशन मास्टर के कर्तव्य (1) 005. आवधिक चिकित्सा परीक्षा (PME) (1) 0051. बोगी कबर्ड बैगनो की जानकारी (1) 0052. कोचिंग स्टॉक का तकनीकी डाटा (1) 0054. LHB कोच की महत्वपूर्ण जानकारियाँ (1) 0056. स्टेशन पर अनिरक्षित किये जाने वाले अन्य रजिस्टर (लेखा विभाग से संबंधित ) (1) 0058. भरे हुए अधिकार पत्र (1) 006. संरक्षा परामर्श फार्म (1) 008. प्रायवेट नंबर शीट (1) 009. स्टेशन संचालन नियम (1) 01.01 History of Rail Transport in India (1) 01.02.Functions of the Traffic Department (1) 01.03. Hierarchical set up and line of control of Operating Department (1) 01.031 Responsibility of Station Master (supervisory) / Station Manager (1) 01.032 Duty of Deputy Station Manager (Outdoor)(Outdoor) (1) 01.033 Duty of Station Master / Manager - Block Station Master / Manager (1) 01.034 Duty of Panel SM (1) 01.036 Duty of Gate Man (1) 01.037 Normal Period Of Preserved - Station Operating Registers and Records (1) 01.04. CONTROL ORGANISATION (1) 01.05. Basic Function of control (1) 01.06. Duties of Control Staff (1) 01.07. Books / documents and basic records to be kept in control office (1) 01.09. Co- ordination between Control and stations (1) 01.10. Registers generally maintained in control (1) 01.11. Items checked by Sr. DOM daily/ regular intervals periodically & monthly (1) 02.01 ट्रेन कंट्रोल एव गाड़िया संचालन में कंट्रोल के जिम्मदारी (1) 02.02 ट्रैफिक कंट्रोल (1) 02.02. Emergency Rescue Operation / Disaster Management (1) 02.03. PREFERENTIAL TRAFFIC ORDER (1) 02.03.पॉवर कंट्रोल (1) 02.04 वैगनो & इंजन की उपयोगिता (ENGINE UTILIZATION) (1) 02.04. Importance of Freight Operation: (1) 02.05. TRANSPORT PRODUCTS (1) 02.06. FREIGHT INCENTIVE SCHEMES (1) 02.07. Rationalization Order (1) 02.08. Development of rail-side warehouses (1) 02.09.. Wagon Pool (1) 02.10. WAGON CENSUS ON BROAD GAUGE (1) 03 - मास्टर चार्ट (MASTER CHART) (1) 03.01. LOCO LINKS AND POWER PLAN CREW LINKS (1) 03.02. 10-Hour Rule for Train Crew (1) 03.03. LOCO MAINTENANCE SCHEDULE (1) 03.05. G D R ( GUARD DRIVER REPORT ) (1) 03.06. NOMINATED INTENSIVE EXAMINATION POINTS ON CENTRAL RAILWAY (1) 03.07. WORKING OF CLAMPED WAGON (1) 03.08. ODC (1) 03.10.1 DETAILS OF BRAKE POWER CERTIFICATE (1) 04 - सुबह की पोजीशन (MORNING POSITION) (1) 04.01. Section Capacity and Throughput (1) 04.08. ROLL ON - ROLL OFF (1) 05 - बगाडी संचालन पर प्रभाव डालने वाले कारक (FATO) (1) 05.01. Systems of Working (1) 05.03. All Communication Failure on Double line (1) 05.04. All Communication Failure on Single line (1) 05.05. TSL working on Double line (1) 05.06. Abnormal Working in Automatic Section (1) 06 - 01.उपनगरीय नियंत्रण (SUBURBAN CONTROL) (1) 06 - 02.एरिया कंट्रोल (1) 06 - 04.सेंट्रल कंट्रोल (1) 06 - 05.Emergency control (1) 06- 03.ट्रेन मैनेजमेंट सिस्टम (TRAIN MANAGEMENT SYSTEM) (1) 06.01. LOCO LINK (1) 06.02. RAKE LINK (1) 06.04. MARSHALLING OF TRAIN (1) 07 - नियंत्रण कार्यालय में विभाग नियंत्रकों के कर्त्तव्य (DUTIES) (1) 07.01. TIME TABLES – INTRODUCTION (1) 07.02. Punctuality (1) 07.03. COACHING VEHICLE CENSUS (1) 07.04. Rules for booking Special Coaches & Special Trains on FTR (1) 07.05. Coaching codes (1) 07.06. ACCIDENT AND SAFETY ORGANISATION (1) 08 - विभिन्न परिस्थियों में खण्ड नियंत्रक (SCOR) द्वारा किये जाने वाले कार्य (1) 09 - सवारी गाडी के कोड (IRCA Rule Book - IV) (1) 10 - संखियकी (STATISTICS) (1) 12 - 01.विशेष प्रकार के माल स्टॉक की मार्शलिंग (1) 12 - 02.माल गाडी का ब्लाक रेक / Standard rake size for Train load (1) 12 - 03.ओ डि सि (ODC) संचालन (1) 12 - यात्री और माल गाडी का ब्लाक रेक (1) 13 - 01.डीविज़न वैगन बैलेंस / (DIVISONAL WAGON BALANCE) (1) 14 - 01.थ्रू -पुट / THROUGH PUT (1) 14 - SECTION CAPACITY) (1) 15 - 01.मालगाड़ी को आदेशित करना (ट्रेन ओर्ड़ेरिंग / TRAIN ORDERING ) (1) 15 - 02.माल गाडी की औसात गति (1) 15 - 03.वैगनो का यानात्रण (Transhipment of Goods) (1) 15 - 07.गाड़ीयो का प्रस्थान पूर्व विलंब (PDD) (1) 15 - मालगाड़ी संचालन (Goods Train Operation) एवं लोड टेबल (1) 15 -06.कन्टेनराईजेशन Container (CONCOR) (1) 16 - 02.समय सारणी (TIME TABLE) (1) 16 - 03.रेक लिंक / (RAKE LINK) (1) 16 - 04.प्लेटफार्म ऑक्यूपेशन चार्ट / (Platform Occupation Chart) (1) 16 - 05.पिट लाइन ऑक्यूपेशन चार्ट (Pit Line Occupation Chart) (1) 16 - 06.विषेश/वी आई पी गाड़ीयो का संचालन (Movement of Special/VIP Trains) (1) 16 - 07.मेला एवं मिलिटरी स्पेशल गाड़ियों का संचालन एवं सावधानियाँ (1) 16 - यात्री गाडी संचालन / Passenger Train Operation (1) 17 - स्टॉक रिपोर्ट / Stock Report (1) 18 - 01.क्रू लिंक (CREW LINK) / लोको लिंक (LOCO LINK) (1) 18 - 02.दस घंटे नियम (10 HOURS RULE) (1) 18 - लॉबी कार्य पध्दति / LOBBY WORKING (1) 19 - 01.इंजन योजना (POWER PLAN) (1) 19 - 02.इंजन की उपयोगीता (ENGINE UTILISATION) (1) 19 - 03.विशिष्ठ उर्जा खपत / SPECIFIC FUEL CONSUMPTION (SPC) (1) 19 - विभिन प्रकार के इंजन और उनक हार्स पॉवर तथा गती (1) 2.1 Various Machines for Track Maintenance (1) 20 - 01. रेशनलाइजेशन स्कीम : / Rationalization Scheme (1) 20 - 02.रोक (BAN) & प्रतिबंध (RESTRICTION) (1) 20 - 03.वैगन पंजीकरण (1) 20 - 04.वैगन उपयोगीता चक्र (WTR) (1) 20 - 05.वेगन सेन्सस / WAGON CENSUS (1) 20 - वैगन उपयोगीता / अधिमान्य यातायात आदेश :(PTO/PTS) (1) 20.06.माल परिचालन सूचना प्रणाली (FOIS) एवं अन्य परिचालन सूचना प्रणाली (ICMS CMS COA ETC NTES) (1) 21 - 01.विधुतिकृत सेक्शन में गाड़िया का संचालन (1) 21 - 02.ट्रैफिक वोर्किंग रूल्स (TWR) (1) 21 - 03.टावर वैगन का संचालन (1) 21 - 04.रेल मंत्रालय के अंतर्गत सार्वजानिक क्षेत्र के उपक्रम और अन्य संगठन (PSUs) (1) 21 - समपार (लेवल क्रासिंग ) (1) 22 - 01.सिगनल को खतरे की स्तिथि में पर करना (SPAD) (1) 22 - 02.गंभीर दुर्घटना SERIOUS ACCIDENT (ऍम 105) (1) 22 - 03.दुर्घटना होने पर खंण्ड नियंत्रक के कर्त्तव्य (AM - ३१९) (1) 22 - 04.दुर्घटना स्थल के प्रभारी अधिकारी के कर्तव्य (AM - 324) (1) 22 - 05.मंडल नियंत्रण कार्यालय के प्रभारी अधिकारी के कर्तव्य - (AM - 323) (1) 22 - 06.दुर्घटना होने पर स्टेशन मास्टर की ड्यूटी (ऍम 311) (1) 22 - 07.रहत व्यवस्थाओ की ओर्ड़ेरिंग देना (AM - 405) (1) 22 - 08.अपघात प्रबंध (DISASTER MANAGEMENT) (1) 22 - 09.गोल्डन ऑवर(GOLDEN HOUR) (1) 22 - 11.नॉन - इंटरलॉकिंग संचालन (Non - Interlocked Working) (1) 22 - दुर्घटना (Accident) (ऍम 104) (1) 22.10 सुरक्षा डेविसस (Safety Devices) - ACD EOIT GSMR TAWD VCD WILD (1) 23 - कंट्रोल ओफ्फिक निर्देश (1) 24 - COA Main Menu (1) 25 - अग्रीम प्लाटिंग (चार्टिंग) / Advance Plotting (1) 26 - 01.नियंत्रण कार्यालय अनुप्रयोग हेतु त्वरित दिशा निर्दश (1) 26 - COA एवं FOIS के एकीकरण (Integration) हेतु अवय्शक निर्दाश (1) 27 - पश्चिम मध्य रेल तथा मध्य रेल के सहायक नियमो में विभिन्नता की सूची (1) 28 - निरीक्षण उसके उदेश्य और प्रकार (Inspection Its Objects & Type) (1) 28.01 Schedule Of Inspection By Operating / Safety Officers And Transportation Inspectors (1) 29 - दुर्घटना जाँच (Accident Inquiry) (1) 3.031 DIESEL LOCO SCHEDULE & DURATION (1) 3.09 ELECTRIC LOCOMOTIVE FEATURES (1) A.01 भारतीय रेल का इतिहास एवं प्रगति (1) A.02. भारतीय रेल का संगठनात्मक ढांचा (1) A.03.परिचालन विभाग का सेटअप (1) A.04. महत्वपूर्ण विभागों के सामान्य कार्य (1) A.05 सामान्य एवं सहायक नियम ब्लाक संचालन नियमावली दुर्घटना नियमावली (1) A.06.परिचालन नियमावली/ संचालन समय सारिणी (1) A.07.स्टेशन संचालन नियम (1) A.08.रेल सेवको पर साधारण लागू होने वाले नियम (1) A.09.महत्वपूर्ण परिभाषाए (1) A.10.सिगनलों का सामान्य परिचय (1) A.11.पटाखा सिगनल (1) A.12.हाथ सिगनल (1) A.13.गाड़ी संचालन पध्दतियाँ (1) A.15.वाहनों को सुरक्षित करना (1) A.17.हॉट एक्सल/फ़्लैट टायर/ओपेन डोर एवं हैंकिंग पार्ट (1) A.18.ट्रेन्स क्लर्क के कर्तव्य (1) A.19.स्टेशनों/यार्ड में रखे जाने वाले रजिस्टर (1) A.20.गाड़ी परिचालन में ट्रेन्स क्लर्क की भूमिका (1) A.21.गाड़ी संचालन से समबंधित महत्वपूर्ण नियम (1) A.22.कंट्रोल संगठन के कार्य (1) A.23.स्टेशन/यार्ड/कंट्रोल आफिस के क्रिया कलाप (1) A.24.विभिन्न प्रकार के कोचिंग एवं गुड्स स्टॉक (1) A.25.ब्रेक पावर प्रमाण पत्र (1) A.26.इंजन एवं ब्रेकयान में एयर प्रेशर की मात्रा (1) A.27.कंटीन्युटी टेस्ट (1) A.28.बड़े आयाम के प्रेषण (1) A.29.सेंसस एवं स्टॉक रिपोर्ट (1) A.30.मालगाड़ी संचालन/ गाडियों को आर्डर करना (1) A.31.डिविजन वैगन संतुलन (1) A.32.इन्टरचेंज (1) A.33.शंटिंग प्रतिबन्ध (1) A.35.वैगन पूल (1) A.36.वैगन उपयोगिता चक्र (1) A.37.परिचालन सांख्यिकी / परिचालन अनुपात (1) A.38.मोर्निंग पोजीशन फैटो (1) A.39.कोचिंग एवं गुड्स गाडियों की मार्शलिंग/घाट मार्शलिंग/रेक मार्शलिंग (1) A.41.जीडीआर चेक/ सेफ टू रन सर्टिफिकेट/ ओवर लोडिंग /अनइव्ह्न लोडिंग (1) A.42.लोड टेबल /एक्सल लोड / बैकिंग इंजन की आवश्यकता (1) A.43.माल गाडियों के विभिन्न प्रकार के ब्रेक पावर प्रमाणपत्र उनकी वैधता (1) A.44.स्थान शुल्क एवं विलंब शुल्क स्केटिंग (1) A.46.लोको आउटेज एवं इंजन उपयोगिता (1) ACF (1) AUTHORITIES USING IN TRAIN WORKING (1) AWS (1) Accident Drill (1) B.02.एफओआईएस/आर एस एम /टीएमएस /सीओआईएस/आईसीएमएस/पीएएम (1) B.05.यूटीएस/ पीआरएस UTS/PRS (1) B.06.ट्रेन मेनेजमेंट सिस्टम (1) B.07.एसीडी / टीसीएएस (1) BOOKED SPEED (1) Block working (1) COA (1) Correction Slip (1) DUTIES OF STATION MASTER IN THE CASE OF ACCIDENTS (1) Department (1) Duty (1) Duty List (1) Flat Tyre (1) Freight Train Operation (1) G.01 Code for LHB Coaching Stock (1) G.01 रेल सेवकों पर साधारणतया लागू होने वाले नियम (1) G.02 G & SR - परिभाषाएं (1) G.02 स्टेशन पर अग्निसमन उपकरण (1) G.03 इन्टरलाॅकिंग एवं नाॅन-इन्टरलाॅकिंग. (1) G.04 पाॅइन्ट एवं सिगनल (1) G.05 विभिन्न प्रकार की लाइटें एवं रिपीटर (1) G.06 संचालन मे आनेवाले विभिन्न प्रकार के बोर्डं (1) G.07 इंजीनियरिंग सिगनल एवं कार्यस्थल का बचाव (1) G.08 सिगनल तथा पाॅइन्ट की खराबी (1) G.09 सिगनल खराब होने पर गाड़ियों का संचालन (1) G.10 कार्य संचालन पद्धति (1) G.11केवल एक गाड़ी पद्धति (1) G.12 सम्पूर्ण ब्लाॅक पद्धति (1) G.13 गाड़ियों का संचालन (1) G.14 स्टेशनों पर बजाई जाने वाली घंटीया (1) G.15 आटोमेटिक ब्लाॅक पद्धति (1) G.16 अनुगामी गाड़ी पद्धति (1) G.17 सतर्कता आदेश (1) G.18 अवरुद्ध लाइन/ बिना सिगनल वाली लाइन व काॅमन स्टार्टर पर गाड़ी का संचालन (1) G.19 शन्टिंग (1) G.21 मार्शलिंग एवं डेड इंजन का संचालन (1) G.21 गाड़ी को स्टेशन से रवाना करना (1) G.23 समयपालन (1) G.24 लोको पायलट व गार्ड के निजी उपकरण (1) G.25 गार्ड व लोको पायलट से संबंधित रजिस्टर व प्रपत्र (1) G.26 रनिंग लाइन पर लोड को स्टेबल व क्लीयर करना (1) G.28 लोको पायलट व गार्ड की ड्यूटी (1) G.29 विभिन परिस्थितियों में लोको पायलट की ड्यूटी (1) G.30 मेटेरियल ट्रेन का संचालन (1) G.31 विभिन्न परिस्थितियों मे स्टेशन मास्टर की ड्यूटी (1) G.32 गाड़ियों की गति (1) G.33 कैच एवं स्लिप साइडिंग (1) G.33 स्टेशनों पर विभिन्न उपकरण (1) G.34 लाॅक एवं ब्लाॅक उपकरण (1) G.35 असामान्य परिस्थितियों में गाड़ियों का संचालन (1) G.36 इंजन सीटी कोड (1) G.37 ई एम यू / एम ई एम यू / डी एम यू में संके तहेतु बेल कोड (1) G.37 नए परिचालन फाॅर्म (1) G.38 इंजीनियरिंग कार्य प्रणाली व इंजीनियरिंग वाहनों का संचाल (1) G.38 पावर ब्लाॅक (1) G.39 पाइथाॅन रैक का संचालन (1) G.40 गाड़ी लिपिक के रजिस्टर व कार्यप्रणाली (1) Group "B" (1) HKT (1) KNOW ABOUT - जन शिकायत पुस्तिका (1) LED Torch (1) Lobby system (1) Loco Pilot Duty (1) MPS (1) Medical Care (1) Pad Lock (1) Private Number (1) Question Bank & Papers With Answer For Group "B" / Guard / Station Master etc Exam (1) Rule. Manual (1) S 01.0 Significance Of Rule Books (1) S 01.01 Differences Between General And Subsidiary Rules (1) S 02.00 Rules And Instructions (1) S 03.00 Rules Applying To The Railway Servant Generally (1) S 04.00 Definition Of Operating Terms (1) S 05.00 Classification Of Station (1) S 06.00 Signals (1) S 07.00 DETONATING SIGNAL (1) S 08.00 Hand Signal (1) S 09.00 Traffic Board And Engineering Indicators (1) S 11.00 CONDITIONS FOR TAKING OFF SIGNALS (1) S 12.00 CONDITIONS FOR CLEARING THE SECTION AND PRECAUTIONS (1) S 13.00 AUTHORITIES USING IN TRAIN WORKING (1) S 14.00 INTERLOCKING AND ISOLATION (1) S 15.00 POINTS (1) S 16.00 WORKING OF TRAINS DURING OVERHAULING (1) S 17.00 DEFECTIVE POINTS (1) S 19 DEFECTIVE SIGNALS (1) S 20.00 Reception Dispatch And Crossing Of Train At Station (1) S 21.00 SHUNTING (1) S 22.00 PUSHING BACK OF TRAIN (1) S 23.00 SECURING VEHICLES AT STATION (1) S 24.00 VEHICLES ESCAPING FROM STATION (1) S 25.00 WORKING OF MATERIAL TRAIN (1) S 25.01 Procedure of sending material train into the Block Section (1) S 25.02 STABLING OF MATERIAL TRAIN (1) S 26.00 HOT AXLE AND FLAT TYRE (1) S 27.00 WORKING OF TRAIN WITHOUT BRAKE VAN (1) S 28.00 STANDARD TIME (1) S 29.00 SPEED CHART (1) S 30.00 ELECTRIC BLOCK INSTRUMENT (1) S 31.00 TAIL LAMP AND TAIL BOARD (1) S 36.00 TRAIN PARTING (1) S 37.00 TRAIN DIVIDING (1) S 38.00 SEND ASSISTING ENGINE INTO OBSTRUCTED BLOCK SECTION (1) S 39.00 TRAIN DELAYED IN BLOCK SECTION (1) S 40.00 ACCIDENT (1) S 41.00 DISASTER MANAGEMENT (1) S 42.00 YARD (1) S 43.00 DUTIES OF STATION STAFF TOWARDS CONTROL (1) S 44.00 WAGON EXCHANGE REGISTER (1) S 45.00 STOCK REPORT (1) S 46.00 WORKING OF TRAIN IN GHAT SECTION / CATCH AND SLIP SIDING (1) S 47.00 MEANS OF COMMUNICATION AND WHISTLE CODE (1) S 48.00 ACTION TAKEN DURING THE ACP (1) S 49.00 WORKING OF TRAIN DURING STORM / ANEMOMETER CYCLONE (1) S 50.00 FIRE IN TRAIN (1) S 51.00 INFORMATION SYSTEM / COA/ FOIS/ ICMS/ PRS etc (1) S 52.00 ACD (1) S 53.00 LOCOMOTIVE LIGHT (1) S 54.00 WORKING OF TRAIN IN ELECTRIFIED SECTION AND TOWER WAGON (1) S 55.00 LEVEL CROSSING GATE (1) S 56.00 OVER DIMENSIONAL CONSIGNMENT (O.D.C. ) (1) S 57.00 MARSHALLING (1) S 58.00 WORKING OF TROLLY/LORRY (1) S 59.00 TYPES OF TRACK MACHINE (1) S 60.00 MANSOON PATROLLING (1) S 61.00 DEFECTIVE PARMANENT WAY (1) S 62.00 WORKING OF LONG HAUL TRAINS (PYTHON) ON CENTRAL RAILWAY (1) S 63.00 HEAVY HAUL TRAINS (1) S 64.00 ABBREVIATION (1) S 65.00 DIFFERENCE BETWEEN SUBSIDIARY RULES OF CR AND WCR (1) SH (1) SPEED ON TURNOUTS (1) Safety Chain (1) Scotch Block (1) Skid (1) Station Earning (1) Station Inspection (1) Train Manager (Guard) (1) VTO (1) Video (1) WORKING OF TRACK MACHINE (TTM etc.) (1) Yard Congestion (1) fois (1) k (1) long Haul (1) योजना बनाने में स्टेशन मास्टर की भूमिका (1) सिगनलों का आदान प्रदान (1) स्टेशन मास्टर अवश्य ध्यान दे (1)